KOREM JSC Announces the Results of the Auction for the Selection of Wind Power Plant Projects in the Northern Zone with a Total Capacity of 100 MW Held on May 19, 2026.

KOREM JSC Announces the Results of the Auction for the Selection of Wind Power Plant Projects in the Northern Zone with a Total Capacity of 100 MW Held on May 19, 2026.

   On May 19, 2026, an auction was conducted for the selection of wind power plant (WPP) construction projects in the Northern Zone of the Unified Power System of the Republic of Kazakhstan, with a total installed capacity of 100 MW.

   Seven companies were admitted to participate in the auction. During the trading session, participants submitted 25 price bids, while the total volume of submitted applications reached 600 MW.

   Following the auction results, Plenitude Kazakhstan was declared the winner. The project’s installed capacity amounts to 100 MW, with an auction tariff of KZT 11.48/kWh (excluding VAT).

   Representatives of the Ministry of Energy of the Republic of Kazakhstan, Qazaq Green Renewable Energy Association, Kazakhstan Electric Power Association, and Atameken National Chamber of Entrepreneurs participated in the auction as observers. The observers confirmed the transparency and proper functioning of the electronic trading system operated by KOREM JSC.

   The next auctions for the selection of WPP construction projects are scheduled for May 20, 2026, in the Northern Zone, with a total installed capacity of 100 MW.

 

 